SickKids
Peter Gilgan Centre for Research & Learning, ICAT
Creative solutions were required to accommodate the extremely intense and sophisticated computer systems within the architectural constraints of this building.
Angus Connect provided a Canadian first — the design and implementation of an HPC-High Performance data centre in a healthcare research facility.
Our recommended technical solution involved an overhead communications wiring system design, using multiple cable trays with an integral cable access management system. This innovative system design solution resulted in considerable space savings over a conventional system. A conventional raised floor communications cabling system was not an option due to space restrictions.
This Data Centre, which supports data cabinets with high performance servers that use 60 KW load, required very large and fully redundant Uninterruptible Power Supplies (UPS) and emergency generator systems to support the critical loads.
The facility has been certified LEED® Gold. The shell and core design were already well along when the Hospital’s High Performance computing group announced their intention to locate all of their high performance computing equipment into the new Data Centre.
SERVICES
Mechanical Engineering | Electrical Engineering | IT Communications Design | Lightining Design
PROJECT FEATURES
Size: 740,000 ft2 | Status: Completed 2013
LOCATION
Toronto, Ontario
KEY SCOPE ELEMENTS
Introduced innovative system solutions for urban-space saving, along with sophisticated computer systems | LEED Gold Certified
Ministry of the Attorney General/Infrastructure Ontario
Thunder Bay Consolidated Courthouse
This multi-storey building features 15 courtrooms, 4 conference/settlement suites, and Ontario’s first aboriginal conference settlement suite. It is LEED® Silver-certified, with barrier-free design, infrared hearing assistance and barrier-free witness stands and jury boxes.
HH Angus provided electrical engineering design, vertical transportation engineering and lighting design for the 8-storey building (seven above grade and one below grade for parking and holding cells). The electrical design features 100% emergency generator backup, UPS (uninterrupted power supply) and inverter lighting systems.
Lighting design included interior lighting, exterior building perimeter and parking. Exterior lighting was designed to be ‘dark sky compliant’, and all lighting design and luminaires targeted LEED® Silver. Custom lighting was designed for the aboriginal conference settlement suite, and featured low energy metal halide T5 fluorescent uplighting for the domed ceiling surfaces and LED downlights for general lighting.
Vertical transportation systems were designed to provide dedicated service for each of the primary forms of facility traffic: public, private (judicial), prisoner and building services. There are twelve elevators in total, the majority of which are Machine-Room-Less (MRL) gearless traction type. This elevator type represented the latest technological advance for energy efficiency and operational performance for low-to-medium rise buildings. Custom cab finishes for the public and private elevators complement the building’s interior design, while the prisoner elevators include an interior partition for the safe movement of accused by security staff.
SERVICES
Electrical Engineering | Lighting Design | Vertical Transportation Design
PROJECT FEATURES
Status: Completed 2014
LOCATION
Thunder Bay, Ontario
KEY SCOPE ELEMENTS
Designed transportation system to provide dedicated service for each form of facility traffic | Custom lighting design for specific conference suite featured low metal halide T5 fluorescent uplighting| MRL gearless traction type was used for - the majority of the elvators| LEED Silver

Built to last
The Courthouse was a design-build-finance-maintain project, with life-cycle repair and renewal responsibilities that ensure the courthouse (including heating and cooling systems, windows, floors, roofing structures and hard landscaping) is kept in excellent working condition over the 30-year period.
20 King St West, Toronto
Damage Investigation & Remediation
Following a hydro vault explosion and fire at 20 King Street West, HH Angus was engaged to provide consulting services for the subsequent investigation, restoration and rehabilitation of the base building core and shell.
20 King Street West is a 250,000 ft2 office building in Toronto’s downtown core. It consists of 15-storeys above grade, including the mezzanine, truss, upper truss and penthouse, as well as two levels below grade.
HH Angus completed a remediation and renewal of all mechanical and electrical components and major equipment that had been severely contaminated or damaged by the fire.
SERVICES
Mechanical Engineering | Electrical Engineering
PROJECT FEATURES
Size: 250,000 ft2 | Status: Ongoing
LOCATION
Toronto, Ontario
KEY SCOPE ELEMENTS
Consulting services for investigation, restoration and rehabilitation of base building core and shell | Remediation and renewal of all mechanical and electrical components and major equipment
Teknion
Tenant Office Fitout
HH Angus’ scope of work required that all design for this ultra modern Toronto office space and showroom target LEED®-CI Gold certification.
A key design challenge for our team was the client’s strong preference for clean ceilings. This meant the design had to minimize conduit runs, devices, etc. Underfloor systems were used in the engineering design to ensure the majority of the mechanical and electrical infrastructure was concealed. The mechanical distribution under the raised floor used Camino systems.
SERVICES
Mechanical Engineering | Electrical Engineering | Lighting Design
PROJECT FEATURES
Size: 10,750 ft2 | Status: Completed 2016
LOCATION
Toronto, Ontario
KEY SCOPE ELEMENTS
Tenant fitout | LEED-CI Gold Certified | WELL Certified Underfloor systems to conceal services | Statement lighting

Site-specific design
Our design team was challenged in locating services and systems, given both raised floors and exposed ceilings. The ceilings featured suspended direct/indirect lighting throughout the space.
Statement lighting design
Speciality and decorative lighting played an important role in this project, from selection of fixtures and providing samples and budgets for client approval, to photometrics to meet showroom conditions.

All Seniors Care Living Centres
HH Angus is providing mechanical and electrical engineering and lighting design to greenfield sites in Kingston, Ontario. The seniors’ care facility feature 170 residential units, plus ground-floor amenities including pool, commercial kitchen, gym, and multi-use spaces.
HH Angus has both long standing and recent experience in the retirement and elder care sectors, including long-term care facilities, complex continuing care, dementia centres, seniors’ homes, hospices, and similar facilities that combine a healthcare setting with a residential component. Over the years, we have developed a sensitivity to the design nuances associated with these facilities.
Our scope includes complete design for the building systems, inclusive of generator site services within five feet of the building, plus complete plumbing and HVAC design.
The building has been classified B3 under the Ontario Building Code, an unusual ‘tall building’ designation for a building of this style and height. This OBC classification required additional ventilation options compared to those required for similar mid-rise apartment buildings.
Effective coordination between disciplines was paramount in order to achieve the high ceilings the client desired. We worked closely with the interior design team, structural engineers and architects in order to deliver this design feature for the client.
SERVICES
Mechanical Engineering | Electrical Engineering | Lighting Design
PROJECT FEATURES
Status: Completion 2020
LOCATION
Kingston, Ontario
KEY SCOPE ELEMENTS
Designed multi-storey long term care residential facility | B3 ‘tall building’ OBC classification | 170 residential units | Introduced multiple options for mechanical system together with estimated ROI

Sharing Expertise with Clients
HH Angus provided multiple options for the mechanical system, together with the estimated ROI for each, to assist the client in selecting the most appropriate equipment for this application.