Toronto Community Housing

341 Bloor Street West, Senator David A. Croll Apartments

“The system brings enormous value to the facility. Not only does it increase the emergency power load to near peak load, but also it reduces emissions and eliminates transmission losses, thus reducing the need for expanded power generation.”  

- Paul Isaac, Principal in Charge, HH Angus

The Senator David A. Croll Apartment building, formerly Rochdale College, is a typical multi-unit residential building managed by the Toronto Community Housing Corporation.

This 335 kW combined heat and emergency power (CHeP) project was built to avoid the cost of replacing a diesel generator, with a significant saving of $300,000. Conventional emergency on-site generation uses dedicated equipment that is rarely operated, yet has a very high capital cost (known as a ‘stranded asset’). HH Angus converted this stranded asset to provide an economic benefit to the facility. The benefit comes from recovering heat so that the overall efficiency rose from 33% to 83%, as well as the use of natural gas, which is cheaper than diesel.

The new generator produces enough electricity for the entire building load on most days. The heat generated by the engine is captured and used to heat the domestic hot water system and building spaces, thereby producing a highly efficient use of the fuel - greater than 90%!

The most important benefit for the building’s occupants is the increased emergency power load capabilities. Instead of powering just a minimum of elevator and emergency lighting services during power outages, the CHeP system provides a power load that runs all regular systems, including heating and air-conditioning systems.

SERVICES
Prime Consultant | Mechanical Engineering | Electrical Engineering


PROJECT FEATURES
Status: Completed 2008


LOCATION 
Toronto, Ontario


KEY SCOPE ELEMENTS
Combined Heat and Emergency Power (CHeP) |  Co-generation tied into a network system, a first for Toronto
| Stranded asset converted to economic benefit - heat recovery efficiency rose from 33% to 83%


A Toronto ‘first’!

The 341 Bloor Street system was a first in Toronto and was carried out with funding assistance from the Toronto Atmospheric Fund and Natural Resources Canada.

Ford Motor Company of Canada

Fuel Cell Building

This building was designed to house Ford’s ‘Fumes-to-Fuel’ technology, which converts toxic volatile organic compounds (VOCs), generated during the painting process, into electricity that powers the plant’s operations. 

The Oakville system began with a 120KW internal combustion engine that was installed as part of this project. Ford had plans to add additional power generating equipment.

HH Angus served as Prime Consultant for a new, state-of-the-art, 10,000 ft2 building to house a patented process for the capture of VOCs from spray booths.

This engineered industrial building, with a height of 35.5 feet, was constructed adjacent to the existing Ford plant, but is not linked to the plant. The building contains a public viewing area for Ford’s green energy system, a training room, offices, warehouse and washrooms. All public spaces were air-conditioned. A steam boiler provides heating for both the fuel cell process and the building. The electrical feed to the building supports both the process and building. It was connected to an existing electrical substation located inside the existing plant.

As Prime Consultant, we were responsible for all architectural, engineering and structural disciplines for the building, as well as site services and associated utilities for the fuel cell process to function properly.

SERVICES
Prime Consultant | Mechanical Engineering | Electrical Engineering


PROJECT FEATURES
Size: 10,000 ft2 | Status: Completed 2008


LOCATION 
Oakville, Ontario


KEY SCOPE ELEMENTS
Engineered industrial building - with a height of 35.5 feet |
Prime Consultant for all disciplines (architectural, structural, mechanical & electrical) as well as site services and associated utilities for the fuel cell process to function properly


The Granite Club

Aquatics Complex

The fourth Granite Club opened in 1972 on a beautiful twenty-two acre site on Bayview Avenue, bordering Toronto’s Don Valley. HH Angus was an integral part of the design and construction team for this premier facility, which provides members with one of the most complete and well-equipped athletic facilities in Canada.

HH Angus is privileged to enjoy a 40-plus-year relationship with the Granite Club and has been involved with many upgrades to the 80,000 ft2 structure since it opened.  

The mechanical, electrical and lighting design for the Aquatic Complex renovation included features such as a competition-scale swimming pool, training pool, whirlpool, and children’s pool with water features. Design of the addition also addressed the retractable roof and retractable perimeter walls.

The retractable roof posed a challenge for our lighting design team, who had to identify the location of the fixed structural members and incorporate the appropriate lighting design to address the sloped roof. The solution was the selection of luminaires and supporting details on the fixed structural members of the roof construction, accommodating the retractable roof elements.

HH Angus has also designed upgrades to seven squash courts, four badminton courts, eight curling rinks and separate skating rink, bowling alley, outdoor lawn bowling area, six tennis courts, and a fitness centre.

SERVICES
Mechanical Engineering | Electrical Engineering | Lighting Design


PROJECT FEATURES
Size: 80,000 ft2 | Status: Completed 2008


LOCATION 
Toronto, Ontario


KEY SCOPE ELEMENTS
Electrical, mechanical, & lighting design for expansion including competition-scale swimming pool, training pool, whirlpool, and children's pool | Retractable roof and retractable perimeter walls


Upgrading sports and fitness facilities

HH Angus has also designed upgrades to seven squash courts, four badminton courts, eight curling rinks and separate skating rink, bowling alley, outdoor lawn bowling area, six tennis courts, and a fitness centre.

— Photos Courtesy Granite Club

University of Guelph

New Science Complex

The University of Guelph undertook an expansion of its Faculty of Science facilities. The complex was constructed in two phases, with the first being a 4-storey, 360,000 ft2 building to house the Departments of Chemistry, Botany, Zoology and Microbiology.

Phase 1 was the 160,000 ft2 New Science Complex. The ground floor is a research module consisting of a large nuclear magnetic resonance suite, electron microscope rooms, and a mass spectrometry facility. An extensive chemical storage area was also located on ground level, and a greenhouse facility was built on the roof.

Phase 2 featured additional graduate research ‘wet’ labs and teaching laboratories in its 200,000 ft2 footprint. An atrium space provided amenities such as a student lounge area and food services facility. Office and support areas were also included.

SERVICES
Mechanical Engineering | Electrical Engineering 


PROJECT FEATURES
Size: 360,000 ft2 | Status: Completed Phase I 2004, Phase II 2006

LOCATION 
Guelph, Ontario


KEY SCOPE ELEMENTS
3 floors of teaching labs, 3 floors of graduate research wet labs | Extensive chemical storage area on ground level | Greenhouse facility on the roof | Office and support areas


Comprehensive Education Centre

The building formerly known as the Sciences, Advanced Learning and Training Centre (SALT) is now called the New Science Complex.

Engineering multiple laboratory types

The Phase 1 facility features three floors of teaching labs for the Chemistry Department and three floors of graduate research ‘wet’ labs.  The ground floor is a research module consisting of a large nuclear magnetic resonance suite, electron microscope rooms and a Mass Spectrometry facility. An extensive chemical storage area is also located on the ground level. A greenhouse facility is located on the roof of this part of the building

Cadbury Canada

Weston Foods Gladstone Avenue Plant

The Weston Foods plant has undergone many mechanical and electrical renovations and upgrades with HH Angus and Associates serving as prime consultant.

Producing chocolate and confectioneries has many challenges. They require viscous fluid pumping and precise control of temperature and humidity levels in order to produce quality chocolate. These engineering challenges were compounded by the plant’s urban location in a residential area, which meant that all amendments to the exterior of the plant had to be compatible with the neighbourhood.

HH Angus was engaged to review the plant, which had been operating for 20 years. This was done to establish current production requirements and to assist in projecting requirements for future growth.

HH Angus’ work at the plant included:

  • Development and construction of a new central plant to provide steam, water, compressed air, refrigeration, and HVAC services for confectionery production. The plant featured a 2000 ton ammonia-to-water process chilling and air conditioning plant to condition 300,000 cubic feet per minute for air conditioning and ventilation of production areas, and for remediation of noise and odours within the plant. Renovation of the office and manufacturing facilities involved relocation of 13 production lines to preferred locations and reworking the electrical power distribution system. During the time the renovation was in progress, production was sequentially phased in selected areas, and high levels of quality production were achieved with no impact on product quality.

Processes and spaces involved in the renovations and upgrades included:

  • Pumping of multiple grades of chocolate with double-walled hot water heated piping for chocolate transportation
  • Pumping of chocolate liquor, fats and food oils, glucose, sugars, caramel, nougat; transport piping and storage tanks
  • Bulk milk delivery with tanker cleaning facilities
  • Freezer storage warehouse space for ice cream
  • Cool storage for chocolates
  • Cold storage for production ingredients
  • Process water recovery system for process chilled, cold and hot water, which reduced plant water consumption with significant savings
  • 50,000 US gallons per day process effluent discharge control system to reduce biochemical oxygen demand and suspend solid level of process effluent to meet stringent City of Toronto requirements
  • Special humidity control (30% RH or lower) for hydroscopic confectionery process rooms
  • Air systems to handle process-generated dust and vapour extraction for peanuts, raisins, alcohol solvent-based candy coatings, and sugar conveying
  • Review of process cooker and votator (scraped surface heat exchanger) of foreign manufacture with respect to ASME pressure vessel code compliance
  • Upgrading of 2200 ton ammonia refrigeration condensing system to all evaporative condensing equipment, with 28 stages of condensing. Design of microprocessor-based control system for: optimized selection of equipment to maintain condensing pressure; automatic selection of quietest equipment for night-time operation; automatic selection/deletion of condensing stages for summer or winter operation.

SERVICES
Mechanical Engineering | Electrical Engineering


PROJECT FEATURES
Status: Completed 2006


LOCATION 
Toronto, Ontario


KEY SCOPE ELEMENTS
Development and construction of new central plant facility | Steam, compressed air, refrigeration and HVAC services | Renovation of office and manufacturing facilities


Working with Affiliates

In addition to the work in the chocolate and confectionery plant, HH Angus and Associates has been involved with Weston Group food plants at:

  • Weston Bakeries
  • Neilson Dairies 
  • Loblaw Supermarkets