Durham Region Transit

Oshawa Bus Maintenance Facility

Durham Region needed to accommodate the repair/maintenance requirements of its fleet of buses with a facility that would be integrated into an existing building. The project is on track for LEED® Silver Certification.

The project features a state-of-the-art Transit Control Centre on the second floor for regional bus and GTAA connection communications. Highlights include state-of-the-art ventilation and exhaust systems, fuel/fluid dispensing, a vacuum cleaning system, parts dispensing, tire storage/ servicing, lubrication stations, paint booths and a bus wash station. The mechanical design scope included plumbing, fire protection, HVAC, controls and process systems and services.  The building was designed to reduce energy and water demand and includes for rainwater storage facilities.

The electrical scope included normal and emergency power systems, fire alarm, state-of-the-art LED lighting and integrated IT System (incorporating time management, clock system, Presto system, communication systems and various radio systems). Durham Region building standards also required design of a lightning protection scheme.

SERVICES
Mechanical Engineering | Electrical Engineering | IT | Security and Communications Design | Lighting Design


PROJECT FEATURES
Size: 60,000 ft2 - 5500 m2 | Status: Completed 2016


LOCATION 
Oshawa, Ontario


KEY SCOPE ELEMENTS
State of the art ventilation and exhaust | Controls & process systems and services | Additional design  for lighting protection scheme | Energy use reduction strategies | Rainwater storage | Designed to achieve LEED Silver


Gas Drive

Slave Lake Pulp 9 MWe Cogeneration Project

Waste-activated sludge is produced in vast amounts at pulp mills, and is generally sent to be incinerated or landfilled, or can be land applied. Any of these options represented a lost opportunity at the Slave Lake Pulp plant in Alberta. The sludge would instead be repurposed to serve as the main ingredient for anaerobic digestion—a reliable, local, ongoing source of renewable energy.

HH Angus designed a 3 X 3 MWe bio-gas fed cogeneration plant for Slave Lake Pulp, a division of West Fraser Mills. The renewable energy technology integrates energy-efficient anaerobic digestion, using the pulp sludge, into the plant’s existing wastewater treatment system. This allows the plant to generate a methane-rich biogas that produces electricity and heat for the pulping process.

Our scope included: engineering electrical power equipment to integrate from the owner’s 13.8kV switchboard into the electrical generation system distribution to connect the cogeneration equipment; electrical design for a new engineered building housing the cogeneration machines and balance of plant; affiliated balance of plant engine electrical support services, such as high and low temperature cooling, exhaust gas heat exchanger and fresh/waste oil, glycol makeup systems, etc.

HH Angus prepared a 13.8kV single line diagram for the electrical system, from the power generation modules through the switchboards, to the interface to the utility service and existing owner’s distribution system; plus preparation of a 600V & 120/208V single line diagram for the generator, building auxiliary and balance of plant services. We also designed protection and control systems, and connection arrangements including SCADA with AESO. 

SERVICES
Electrical Engineering | Commissioning support


PROJECT FEATURES
Status: Completed 2015


LOCATION 
West Fraser Mills, Alberta


KEY SCOPE ELEMENTS
Designed a 3 X 3 MWe bio-gas fed cogeneration plant |  Detailed design of power equipment to integrate to utility and owner’s existing plant | Initiated protection and control system designs Including connection arrangements - SCADA with AESO


Proven protection

We provided a detailed short circuit analysis and co-ordination protection setting study to satisfy the owner that their system is fully protected.

Energy win-win 

“This system will now allow us to actually take advantage of some of this lost energy, while also reducing our consumption.”*

Rod Albers, Manager of Energy ad Bio-Product Development, West Fraser Mills

Temporal Power

Flywheel Energy Storage

“With thorough project management and smart engineering by the Angus team, they have been able to condense the schedule and, at the same time, lower our costs.”

 Geoff Osborne, Senior Associate, NRStor

HH Angus and Associates was engaged to provide the detailed electrical engineering and construction management of this flywheel energy storage project at Temporal Power’s Minto facility near Harriston, ON. Flywheel-based energy storage systems do not use fossil fuel and do not produce CO2 or other harmful emissions during operation.

Our electrical team provided consulting engineering to connect Temporal Power’s nominally 2MW of flywheel energy to (and from) the grid at distribution voltage, as well as commissioning of the site.

Grid frequency regulation is required by the IESO in the area northwest of Guelph because of fluctuating electrical load and generation; 2 MW of flywheel capacity can act as a sink or a source of electricity to stabilize frequency.

The vulnerability of the electrical grid and distribution service, as evidenced in the December 2013 ice storm that affected predominantly Ontario, Quebec and the Northeast US, is giving impetus to the move to smart grids, distributed power and storage systems. The Temporal Power facility serves to balance the system frequency, thereby reducing the need to have a more expensive and less responsive generating plant performing that function.

Each of the ten 250 KW flywheels in the plant weighs about 4000 kilos and spins at up to 11,000 RPM.The flywheels operate through five 480V inverters (ie, two flywheels per inverter, with one redundant unit). HH Angus designed and supplied the system that converts the local grid distribution voltage of 44,000V through 347/600V to 480V (and vice versa). In terms of interconnecting to the grid, this is very much like a generator project in that it does ‘generate’ 2MW when requested as frequency is decreasing. But it can also absorb energy when the grid frequency is ‘speeding up’.

SERVICES
Electrical Engineering | Site Commissioning 


PROJECT FEATURES
Status: Completed 2014


LOCATION 
Harriston, Ontario


KEY SCOPE ELEMENTS
Detailed electrical engineering and construction management of flywheel energy storage project | 2 MW of flywheel energy to/from the grid | EPC through Angus Power | Flywheel technology balances system frequency 10 X 250kW flywheels


Engineer
Procure
Construct

This was a substantial EPC project that married the electrical engineering capacity of HH Angus’ grid connection specialists with the project and risk management experience of our Angus Power team.

Hatherley Solar

250kW Photo Voltaic Installation

HH Angus provided full EPC services for this system, including electrical design, panel layout, structural review, component procurement and the installation of the system, commissioning and connection to the grid.

Hatherley Solar is a 250 kW, 36,000 ft2 rooftop solar PV project atop two industrial buildings at the Parry Sound airport in Ontario.

This project received an Ontario FIT contract, and at the time, was the largest solar installation in the Muskoka region, with over 1000 modules on two steel-roof buildings, feeding over 325,000kW hours to the Ontario power grid annually.

 

 

SERVICES
Project Design | Project Management


PROJECT FEATURES
Size: 36,000 ft2 Status: Completed 2014


LOCATION 
Parry Sound, Ontario


KEY SCOPE ELEMENTS
Ontarian FIT contract | Largest solar installation in the Muskoka region | Feeds over 325,000kw hours to the Ontario power grid annually


TELUS

Super Internet Data Centre, Kamloops BC

“The Kamloops Internet Data Centre will be the cornerstone of our national next-generation cloud computing services, handling complex data storage and offering unsurpassed connectivity, superior functionality, state-of-the-art security and industry-leading reliability to our clients.”*

Lloyd Switzer, TELUS Senior VP, Network Transformation

The new TELUS Tier III design-certified data centre was the first TELUS Super Internet Data Centre built to LEED Gold standards. It is directly connected to the national TELUS IP network and interconnects into existing data centres across the country, creating what has been described as the most advanced and regionally diverse computing infrastructure in Canada.

The Intelligent Internet Data Centre incorporates innovative, non-traditional solutions, such as a closed-loop cooling system that provides unparalleled operating efficiency. The first of its kind in the world, this system is 180 times more efficient than that of a traditional cooling plant.

TELUS reports a PUE** of 1.15 for the data centre, which put TELUS at the forefront of the industry. The new data centre has a modular design, enabling TELUS to rapidly expand capacity and to tailor its offerings to the most advanced and efficient technologies available.

SERVICES
Mechanical Engineering |  Electrical Engineering |  Security Design | IMIT Engineering | Vertical Transportation Consulting | Lighting Design


PROJECT FEATURES
Status: Completed 2012


LOCATION 
Confidential


KEY SCOPE ELEMENTS
Modular construction with reduced on-site fabrication | Inaugural installation of patented cooling system


Ensuring Quality Control

HH Angus acted as the Owner’s Commissioning QC Representative. Our responsibilities included review of the commissioning plan, the schedule and test scripts prepared by Commissioning Agent and the site observation reports to the stakeholder team - these covered the 27.6kV incoming switchgear complete with automatic transfer scheme, diesel rotary UPS system, automatic transfer switches, 600V distribution switchboards, Electrical Monitoring System (EMS), ISOT and Black Start Testing.

Tier III Accreditation

HH Angus was the Owner’s representative for the Uptime Institute On-Site Tier III Accreditation Audit.

**PUE, or Power Usage Effectiveness, is the Uptime Institute’s classification system, an internationally recognized benchmark to assess  data centre reliability.

*BC Tech News: TELUS OPENS 75 Million Next Generation Cloud Computing Data Centre in Kamloops