WPP

Toronto Waterfront Campus

WPP Group's building is part of the largest urban revitalization project in North America, bringing together new businesses, restaurants, and transport connections.

Work Design Magazine March 28, 2023

This cutting-edge project on Toronto’s downtown waterfront represents an evolution in commercial office development and reinvents how employees work together in Toronto’s rapidly evolving creative and technology sectors. The new space merges a large number of WPP’s operating companies and 2,000 employees into the top seven floors of the Waterfront Innovation Centre at the city’s iconic ‘Sugar Beach’.  HH Angus provided engineering consulting services for this 250,000 ft2 tenant fitout project. WPP is the anchor tenant for the Waterfront Innovation Centre.

The fitout included raised floors for underfloor HVAC systems and is targeting LEED Platinum certification. On each floor, the design features a café, hub and IT equipment room, with one single Main Communications Room.

The 8th floor has a custom production area with very specific acoustic requirements. Our mechanical team worked closely with the acoustical consultant to provide a design that meets the strict acoustic requirements for  video and audio production and recording. This was achieved through careful placement of fan-powered boxes equipped with silencers. The production area includes multimedia studios, photo studios and a print lab. Lighting control for these rooms is enhanced with tunable lighting, allowing users to adjust the colour temperature in real time.

The 10th floor is the client-facing floor and includes meeting rooms with fully-integrated AV, smart lighting control, open ceiling design concept (industrial design), a large point-of-sale catering kitchen with back of house facilities and an outdoor terrace.

Our communications team designed several interconnecting fibre risers to provide the client with the most cost effective solution and full redundancy to meet their current and future needs, and to ensure the system will continue to operate in the event of external critical failures.

SERVICES
Mechanical Engineering | Electrical Engineering | Communications Design


PROJECT FEATURES
250,000 ft2 colocation project unifying 28 different companies | Seven-floor fitout | Status: Completed 2022


LOCATION 
Toronto, Ontario


KEY SCOPE ELEMENTS
WELL design principles | Pressurized raised floor systems with underfloor HVAC systems | Rigorous acoustic requirements for audio and video recording | Redundant interconnecting communications fibre risers to ensure system will operate in the event of external critical failures


Interior of WPP building
Interior Cafe of WPP building

The Co-operators

Guelph Headquarters

The Co-operators’ Headquarters in Guelph, Ontario has been certified a 'Zero Carbon Building' by the Canada Green Building Council. The project is also targeting LEED Gold and WELL Platinum.

The renovation project covers three floors totalling 226,000 ft2, and includes a data centre, cafeteria, fitness centre, conference rooms, and three-storey open atrium. HH Angus provided mechanical and electrical consulting engineering, as well as IMIT and lighting design.

The building features an all-electric design to eliminate direct carbon emissions from any on-site source. This means that the company did not need to undertake any retrofits or decarbonization plans to achieve net zero targets. The building has been designed to be highly energy-efficient and to minimize indirect annual carbon emissions from electricity.

Any remaining emissions will be offset through high-quality carbon offsets or carbon-free renewable energy sources. The construction process was also meaningfully reduced, offsetting “embodied carbon” emissions resulting from the manufacture, transportation, and disposal of all building materials.

The Canada Green Building Council has identified the building sector as Canada’s third-largest emitter of greenhouse gases (GHG). Presently, residential, commercial, and institutional buildings are responsible for 17% of Canada’s GHG emissions, and this figure approaches 30% when building materials and construction processes are taken into account.

Despite an aggressive construction schedule, the project overcame the challenges of integrating an all-electric design and achieving Zero Carbon Building certification. It also intended to surpass goals for energy and GHG savings beyond the Ontario Building Code’s all-electric baseline and heating load reduction minimum for new builds. The building features a rooftop solar array and a high-efficiency water source, showcasing innovative approaches to sustainable design.

The building’s low-impact features include:

  1. Energy and GHG savings 40% greater than the Ontario Building Code’s all-electric baseline
  2. 60% reduced heating load, surpassing the minimum code requirement for new office builds requirement for new office builds
  3. A 282 kW rooftop solar array that is expected to produce ~9% of the building’s annual total energy
  4. Automatic window tinting to reduce glare and save energy
  5. A highly-insulated and airtight envelope to conserve energy
  6. High-efficiency water source technology to recover and redistribute heat throughout the building
  7. LED lighting equipped with occupancy and daylight harvesting sensors that turn on only when needed

Read CaGBC's feature article about The Co-operators Guelph Headquarters.

SERVICES
Mechanical Engineering | Electrical Engineering | IMIT Consulting | Lighting Design


PROJECT FEATURES
226,000 ft2 | Status: Completion 2024 | Certified ‘Zero Carbon Building by CaGBC  | Targeting LEED Gold and WELL Platinum certifications | LED lighting | Daylight harvesting


LOCATION 
Guelph, Ontario


KEY SCOPE ELEMENTS
Energy and GHG savings 40% greater than all-electric OBC standard | Building designed to achieve net-zero through all-electric design, without retrofits or decarbonization | Targeting reduced embodied carbon emissions during construction, minimizing carbon footprint


Modern reception area with seating

Zero carbon building

The building has attained the ‘zero carbon building design standard’ certification and is pursuing LEED Gold and WELL Platinum certifications.

Carbon offsets

The company will be offsetting embodied carbon emissions resulting from construction, manufacturing, transportation and disposal of all building materials.

Image of modern cafeteria with contemporary furnishings
Modern open interior
Modern open interior person sitting
Modern open interior person sitting at round table

*Source: HOK Canada

AstraZeneca 

Tenant Fitout

“The goal of AstraZeneca’s iWORK workplace strategy is to create facilities that meet expectations of how a great place to work should look and feel.”

AZ Workplace Strategy Guidelines

A further goal of the fitout was to use available space more efficiently to create more collaborative, vibrant working environments to achieve a science-driven, patient-focused culture and mindset.

HH Angus provided M&E consulting engineering and IMIT communications design to the project, which presented a number of interesting challenges requiring thoughtful solutions. Among the challenges was an aggressive schedule. The team worked efficiently and collaboratively to meet the project deadlines.

The project did not allow for core drilling to feed workstations or standalone furniture. To address this, the design team and engineers had to be strategic in using perimeter and under-carpet raceways to conceal wiring. A new lighting design was implemented throughout the 5th floor, and provided a sophisticated wireless lighting control system, complete with daylight harvesting and an occupancy setting, independent of the base building control system.

During the schematic design phase, our team noted several deficiencies within the existing base building system affecting the project’s location. We requested the team have a complete site audit done by a local air balancing contractor, which identified several issues with duct connections, system operation and controls. Through this process, we were able to rectify many issues prior to the close-out phase of our project. This resulted in an efficient transition for the client, saving them both time and money.

SERVICES
Mechanical Engineering | Electrical Engineering | IMIT Consulting


PROJECT FEATURES
Size: 72,000 ft2 designed for two floors of tenant fitout (one floor constructed) | Status: Completed 2021


LOCATION 
Mississauga, Ontario


KEY SCOPE ELEMENTS
Open floor layout accommodated despite base building risers | Base building deficiencies identified, saving client time and money | Team exceeded contract obligations in protecting client from added costs due to COVID pandemic and to ensure timely project completion


Office interior with colourful geometric dividers feature walls

Open concept design

The client had expressed a preference for an open floor layout; however, several of the base building risers were in locations not conducive to the planned interior design. In order to accommodate the client’s wishes, we proactively identified a new shaft location, and re-routed various systems to deliver the floor layout desired by the client.

Pandemic response

The COVID 19 pandemic began in the midst of construction. The project team reacted immediately during these challenging times by providing effective and responsive coordination virtually. The team worked through construction-related delays, and helped mitigate supply distribution delays by using local contacts to expedite shipping to meet the client-requested deadlines.

Interior office shot meeting room with TV and glass walls
Modern interior cubicle with yellow details and man at workstation
Office interior modern kitchen and eating area

The McEwan Group

Fabbrica TD

Fabbrica's second location was designed as a take-out venue. The 4200 ft2 retail space is accessed via Toronto's underground PATH system, in the heart of the city's financial district. Fabbrica on the PATH joins its sister outlet across the hall, the McEwan grocery store.

HH Angus was engaged to provide mechanical, electrical and lighting design services for the tenant fitout of the new Fabbrica on the concourse level of the TD Centre. Fabbrica took over an existing space which required ceiling demolition in order to install new lighting and electrical systems.

Custom interior lighting was designed to attract the attention of commuters and shoppers in the PATH system. To achieve this, 3500K 12W high-colour-rendering LEDs were incorporated into the lighting design to showcase the vibrant colours of the meal offerings prepared for hungry consumers.

The project's location in the concourse level posed a design challenge to the team, due to the modest amount of ceiling and underfloor clearance. To accommodate these restrictions, HH Angus designed solutions to manage the routing of piping, conduits and drainage within the limited space. 

SERVICES
Mechanical Engineering | Electrical Engineering | Lighting Design


PROJECT FEATURES
Size: 4,200 ft2 | Status: Completed 2018


LOCATION 
Toronto, Ontario


KEY SCOPE ELEMENTS
Limited space above and below the retail space required innovative design approaches | High Colour Rendering LEDs


Image of Fabbrica modern interior with worker and cooler

 

Confined spaces

The space restrictions of the site, with regard to M&E infrastructure, required extensive site surveys, plus special attention being paid to obstructions in the parking levels below.

Interior of Fabbrica kitchen with prepared pizza
Interior of long prep area with wall graphics

The Cooperators Canada

Tenant Fitout

“Our people will have first class work environments that support their wellbeing and set the bar in our industry when it comes to workplace design and sustainable construction.”
Shawn Fitzgerald, VP Enterprise Procurement/Workplace Services, The Cooperators

HH Angus designed a complete fitout, including mechanical, electrical, ICAT, and emergency backup power design for this 9-storey renovation. Each floor was a mix of open office and collaboration spaces with ancillary serveries. The second floor had a full commercial kitchen and café area.

Among the challenges of the project was the existing building back up power system, which was not configured to support the new equipment our client desired. We worked closely with our client’s landlord and building managers to find a solution that provided the client with the ability to operate 24/7 without overloading the existing system’s capabilities. Through careful calculations and creative thinking, we were able to reconfigure the existing MCC (motor control centre), and transfer the most crucial items onto the generator system.

Our team worked closely with the return-to-base engineers to relocate new infrastructure within their project scope, in order to ensure work did not need to be duplicated later in our scope. A good example of this was collaborating on new heat pump locations. Since many locations on the floor plates have exposed ceilings, we ensured heat pumps were being located optimally during the back-to-base work, removing the requirement for our project to move them.

When the COVID-19 epidemic became a factor in the late stages of the project, our team quickly adapted to ensure trades were kept accountable and on schedule for project delivery.

SERVICES
Mechanical Engineering | Electrical Engineering | ICAT Design | Audio-Visual Design | Communications Design


PROJECT FEATURES
Status: Completed 2020 | 9 storey complete fitout | Each floor a mix of open office and collaboration spaces | Ancillary services – full commercial kitchen and café


LOCATION 
Regina, Saskatchewan


KEY SCOPE ELEMENTS
9 storeys | Equipment retrofit for existing emergency power system | Detailed coordination with interior design team for multiple ceiling arrangements | Participated in value engineering discussion to meet client’s needs within available budget


Interior of office space at The Cooperators Canada
Interior photo of The Cooperators Canada